How to Accept a New Fibre Installation: Loss Testing, OTDR and Documentation

Check that a contractor's fibre installation meets specification before you sign off: inspection, loss (Tier 1) and OTDR (Tier 2) tests, pass criteria and the documents to demand.

Intermediate9 min6 steps

Before you start

  • The design: link lengths, connectors and splices per link
  • The applicable standard and loss limits
  • Access to the installer's test equipment results

Step by step

  1. Agree the criteria in advance

    Specify standards, maximum loss per link (calculated from length, connectors and splices), and required test types in the contract.

  2. Inspect connectors

    Every connector should be inspected and clean before testing.

  3. Tier 1: loss testing

    Measure end-to-end loss with a light source and power meter at the right wavelengths (for single-mode, typically 1310 and 1550 nm), in both directions.

  4. Tier 2: OTDR traces

    OTDR traces show each connector and splice. Check that no event exceeds its limit and that lengths match the design.

  5. Check labels and records

    Labels on panels and cables must match the documentation.

  6. Collect the documents

    Ask for test reports for every fibre, OTDR files, as-built drawings and warranty documents before sign-off.

Pro tips

  • Keep the reports: they are your baseline for future faults.
  • Spot-check a few links yourself.
  • Reject links that fail rather than accepting 'it works for now'.